- Published by:
- Department of Government Services
- Date:
- 26 Aug 2026
What are the differences between the eServices Short Form Contract and Long Form Contract?
They’re more similar than different
The Short Form and Long Form Contracts are mostly similar and operate in largely the same way. The Long Form Contract has additional and more granular protections compared to the Short Form Contract.
As a rule of thumb, the Short Form Contract will be appropriate for most low risk or simple procurement activities. The Long Form Contract may be used if the procurement activity is complex, high risk or valued at more than $1 million (excl GST).
If you are a Purchaser seeking advice on which provisions are suitable for your project, you should consult your legal team.
Summary of differences between similar provisions
The table below summarises the main differences between equivalent provisions in the Short Form Contract (SFC) and Long Form Contract (LFC). This table is not an exhaustive list of all differences between the two.
Table legend:
N : clause is not included
Y : the equivalent clause is included
! : some similarities in the included clauses, but not identical clauses
| Reference | SFC | LFC | Description |
|---|---|---|---|
Transition In Clause 4 of LFC | N | Y | If specified in the Requirements, the LFC requires the Supplier to provide Transition In Services at no additional cost to the Purchaser. |
Consequences of non-performance Clause 5.4 of LFC | N | Y | The LFC contains specific permission for the Purchaser to require the Supplier to remedy or re-perform non-compliant Deliverables or Services within a reasonable timeframe and to withhold payment for them until that is done. If the failure is not remedied in time, or cannot be remedied, the parties may meet to try to agree a remedy. Where a meeting is not practicable, no agreement is reached, or an agreed remedy is not implemented, the Purchaser may (itself or through a third party) remedy or re-perform the Deliverable or Service and recover all reasonable costs of doing so from the Supplier. |
Access to Purchaser's items and premises Clause 6 of SFC and clause 7 of LFC | ! | ! | In both the SFC and LFC, the Purchaser can provide the Supplier access to the Purchaser’s premises. The Supplier is required to avoid causing harm, act safely and lawfully, and comply with applicable occupational health and safety laws.
|
Consequences of Delay Clause 8 of SFC and | Y | Y | In both the SFC and LFC, the Purchaser can terminate the contract immediately if the Supplier does not provide the eServices by a due date, and the delay persists after the relevant cure period. |
| N | Y | In the LFC only, the Purchaser may claim liquidated damages for the Supplier’s delay if set out in the Ordering Document. | |
Service Levels and Credits Clause 10 of SFC and | Y | Y | In both the SFC and LFC, the Supplier must meet and report on Service Levels. |
| N | Y | In the LFC only, the Purchaser may claim Service Credits for service level failures by the Supplier and require them to undertake root cause analysis and provide a remediation plan to the Purchaser. | |
Conflict of Interest and probity events Clause 15 of SFC and | Y | Y | In both the SFC and LFC, the Supplier is required to warrant that they do not have any conflicts of interest. The Supplier must also notify the Purchaser if they are subject to an actual, suspected or likely Probity Event or Probity Breach (which includes a Supplier’s conflict of interest, breach of the Supplier Code of Conduct, and a matter that brings the Purchaser into disrepute). |
| N | Y | In the LFC only, the Supplier must provide conflict of interest declarations if specified in the Requirements of the Ordering Document. | |
Use of Gen-AI Clauses 19 and 23 of SFC and clauses 20 and 24 of LFC | Y | Y | The Gen-AI provisions are the same in the SFC and the LFC. Under both contracts the Supplier must not provide or use Gen-AI unless the Ordering Document allows it or the Purchaser approves it in writing, must not use the Purchaser’s data to train Gen-AI without approval, and must notify and respond to AI Incidents. Human oversight obligations apply where the Ordering Document says they apply. |
Business Continuity and Disaster Recovery Clause 25 of LFC | N | Y | In the LFC only, the Supplier must maintain and comply with business continuity and disaster recovery plans in accordance with good industry practice, or as otherwise set out in the Requirements. This includes testing the plans at least annually and providing evidence to the Purchaser of their testing if the Purchaser asks for this. |
Indemnities Clause 24 of SFC and clause 26 of LFC | ! | ! | In both the SFC and LFC, the Supplier must indemnify the Purchaser against any losses or damages arising from an IP claim or breach of law.
|
Liability Clause 25 of SFC and clause 27 of LFC | ! | ! | In both the SFC and LFC, each party’s total liability is capped at the General Liability Cap set in the Ordering Document, and neither party is liable for Consequential Loss. Both contracts also allow an optional super liability cap for liability relating to privacy or information security. Some liabilities are not capped under either contract, including death, personal injury, damage to tangible property, breach of confidentiality, fraud, recklessness or wilful misconduct, and the Supplier’s indemnities. Because the LFC contains a wider set of Supplier indemnities, the uncapped exception covers more ground under the LFC. |
Contract Management Clause 29.1 of LFC | N | Y | In the LFC only, the Supplier must provide the Purchaser with the reports and attend the meetings specified in the Requirements, comply with the Purchaser’s reasonable directions and provide the Purchaser with information required to supervise or review the Deliverables and Services. |
Archival requirements Clause 29.5 of LFC | N | Y | In the LFC only, the Supplier must comply with, and assist the Purchaser to comply with, applicable State and Commonwealth legislation relating to archival requirements. |
Transition Out Clause 33 of LFC | N | Y | In the LFC only, the Supplier must provide transition out services as set out in the Requirements. On termination or expiry, the Supplier must stop using the Purchaser’s data, confidential information and related materials. Under the LFC, that requirement does not apply to the extent the Supplier needs continued use to provide transition out services. The Supplier’s confidentiality obligations themselves continue to apply in full. |

